INCHING CLOSER BUT…

 

Phew! We have essentially completed our build-out – Here’s our Tap Room (awaiting sinks and taps to be installed):

Here’s the reverse angle, note the mezzanine will serve as a stage for live music during events, private parties and possibly during Tap Room hours:

And the heart of our brewery, our brewhouse:

So far so good but wait – since Sandy struck (fortunately no damage to our space) the NYC Dept of Buildings has essentially stopped issuing inspection dates.

This impacts us in that we need our final building inspection to secure our State license (our State license has been approved and is waiting on our building inspection to be issued). There are a host of other related approvals we require all at a standstill thanks to the Dept of Buildings.

You can imagine this is extremely frustrating for us. We are reaching out to a number of influencers to try and jog something loose from the Dept of Buildings. We’ll update you with any updates as we have them. Hang in there y’all! – Rulpsen